An AMPROTEQ APEX 20 ft battery container on a concrete apron in front of a data-centre hall at night
Visualisation
Industries · Data centres

Battery storage for data centres.

A data centre buys power every half-hour of the year. Storage takes the campus out of the peak windows, holds its demand under the ceiling and shares the load with the standby sets when the grid goes. The UPS stays as it is.

01 · The problem

What the site
is up against.

Peaks

A flat load, billed at peak

IT halls run around the clock, so the campus buys as much energy in the peak windows as at night, at several times the price.

Demand

Cooling sets the ceiling

Chillers push demand up in the afternoon heat, and one hot half-hour sets the demand charge for the month.

Growth

New halls need headroom

Each new hall adds one or two megawatts against a notified demand the utility is slow to raise.

02 · What storage does

What the battery
does about it.

  1. 01
    Peak shiftingCharges off-peak and at midday, and carries the campus through both peak windows.
  2. 02
    Demand ceilingDischarges when the cooling plant pushes demand up, and frees room under the NMD for new IT.
  3. 03
    Standby supportShares the load with the standby sets in an outage, so they run lighter and burn less fuel.
  4. 04
    Beside the UPSThe UPS keeps its milliseconds. A PULSE transfer cabinet protects critical 400 V boards where they need it.
03 · Typical configuration

Indicative,
before the load study.

SystemsAPEX A5000 blocks (5 MWh, 20 ft) with NEXUS N2500 MV skids
Connection22 kV on spare MV bays (10–35 kV)
DurationAbout 2 hours, sized against the peak windows
Pairs withThe existing UPS and standby sets; PULSE on critical 400 V boards
Commercial modelPurchase; under four years simple payback in the modelled case

Every configuration is sized from the site's own interval data and tariff; this is a starting point, not a quote.

Part one

Where a data centre’s money goes, and how storage brings it back.

The four-page sector brief, on the page: what a campus pays for in Eskom’s peak windows and on its notified demand, the system we connect at 22 kV beside the UPS, the option that keeps the cooling running through a transfer, and what it returns.

Download the flyer
04 · Where the money is

A load that never sleeps,
priced by the half-hour.

The IT load is flat, so a data centre buys as much energy in the peak windows as at night. The battery earns in that gap, and in the demand the cooling plant no longer sets.

Fig 04-1 · Average high-season weekday, 20 MVA colocation campusModelled · MW
PEAKPEAK081624MWIT hallsUPS & lossesCooling plantOffices & servicesDEMAND CEILING 17.4 MW00:0003:0006:0009:0012:0015:0018:0021:0024:00

The white line is grid draw with a 10 MW / 20 MWh plant: lower through both peak windows, refilled at midday and overnight, never above the 17.4 MW ceiling.

Megaflex 2026/27 · 500 V – 66 kVc/kWh ex VAT
High-season peak720 cHigh-season standard180 cOff-peak, all year120 cLow-season peak299 cLow-season standard168 c

Active energy, transmission zone 0. Plus R62.55/kVA a month on the notified demand and R26.29/kVA a month on the highest chargeable half-hour. A kilowatt-hour moved from off-peak (1.20) into a winter peak (7.20) is worth about five times what it cost, after losses.

Where the battery fitsOur view
LoadPatternBattery role
IT hallsFlat, 24 / 7, growingPeak shifting
Cooling plantAfternoon heatDemand ceiling
UPSMilliseconds to minutesStays as it is
Standby setsHours, on an outageRun lighter, burn less
New hallsSteps of 1 – 2 MWRoom under the NMD
20.2R mGross saving, year oneAt FY2027/28 prices
34%Less energy bought in peak6.6 GWh moved a year
2MVAOff the notified demandLower the NMD, or fill it with IT
<4yearsSimple paybackOn an indicative turnkey cost
05 · The system

Beside the UPS,
never instead of it.

The UPS keeps doing what it was designed for. The battery works upstream, at 22 kV, on the bill every day and beside the standby sets when the grid goes.

Fig 05-1 · Three layers of supply, by how long each one carries the loadLog scale
1 ms10 ms0.1 s1 s10 s1 min10 min1 h1 dayPULSE switch400 V boardsUPSIT loadStandby setswhole siteAPEX + NEXUS22 kV, whole site20 ms · ITICMoves the bus to the battery in ≤ 10 ms, inside the 20 ms IT power supplies ride throughHolds the IT load from the first millisecond · minutes of autonomy, unchangedStart and close in 10 – 15 s · run for as long as there is fuelShares the load with the sets, up to 2 h

Nothing in the critical path changes: the UPS still holds the IT load through the transfer and the sets still start on every outage. The battery adds a fourth layer that shortens the sets’ work, and on critical 400 V boards PULSE keeps pumps and air handlers turning through the switch.

06 · Option

Keep the cooling running
through the switch.

The UPS carries the IT load through a transfer; the cooling plant usually is not on it. An A2000 behind a PULSE on the mechanical board closes that gap.

Fig 06-1 · A data-hall mechanical board with PULSE and an A2000Simplified
GRID 400 VSTANDBY SETGPULSE P1000static switch≤ 10 ms400 V BUSA2000 · 1 MW2 088 kWh · 400 VChilled-water pumpsprimary and secondary loopsAir handlersCRAH units and fan wallsSolaris EMS runs the switch, the battery and the standby set start
01Cooling that keeps moving

PULSE moves the mechanical board to the battery in ≤ 10 ms. Pumps and air handlers keep chilled water and air flowing while the sets start.

02No cold start at the worst moment

The cooling board never drops, so there is no restart sequence while the halls are warming.

03One frame per board

P500, P1000 or P2000 per mechanical board, with one or two A2000 systems behind it at 400 V.

04An option, not in the payback

Added on top of the 22 kV plant where the cooling design calls for it, and priced per board.

07 · The return

An asset that pays for itself
in less than four years.

Figures from the modelled campus on this page, at an indicative turnkey cost. A site proposal replaces them with your own.

<4yearsSimple paybackOn an indicative turnkey cost
39%Project IRR, 15 yearsAfter O&M and augmentation
8.4×The investment, returnedNet cash over the term
Three ways to buy
Purchase Most operators

Turnkey supply, install and commissioning. You own the plant; we run it under a 15-year O&M and availability agreement.

Service agreement

We own and run the plant for a fixed monthly fee, for operators who keep storage off the balance sheet.

Phased

Start with two blocks on one bus section and add pairs as new halls are let and the next bay is free.

Load study to power in 38 weeksIndicative
WEEK 1Load studyyour data, our modelWEEK 6Proposalsizing, price, termsWEEK 14Studies and ordergrid, protection, change controlWEEK 28On sitedelivery, civils, cableWEEK 38Powercommissioned
Part two

Taking a colocation campus out of the peak.

Illustrative case · composite site · not a client project

The eight-page business case, on the page: a composite 11.6 MW-IT colocation campus in Midrand, modelled half-hour by half-hour for a year on the real 2026/27 Megaflex tariff at 22 kV, then carried over fifteen years.

Download the business case
08 · The site

A campus that never
stops drawing.

The modelled campus runs every hour of the year. Its bill is R310 m, and 32 % of the energy cost is bought in 14 % of the hours.

Site profileComposite
OperationColocation, four data halls
RegionMidrand, Gauteng
SupplyTwo 22 kV feeders, Eskom direct
TariffMegaflex Me02N, zone 0
IT load11.6 MW average, filling
Annual PUE1.32
Notified demand20 000 kVA
Recorded peak19 639 kVA
Power factor0.95 lagging
Standby10 × 2 MW sets on the 22 kV bus
Annual energy134 GWh
Annual billR310 m ex VAT
Annual bill, beforeR m ex VAT
Energy, peakR77.5 mEnergy, standardR89.0 mEnergy, off-peakR75.4 mLevies & subsidiesR47.0 mCapacity chargesR15.1 mNetwork demandR5.7 mReactive energyR0.3 m

Peak energy costs about as much as all off-peak energy, in a seventh of the hours. It is the line the battery attacks first.

Energy by end useGWh a year
IT halls102 GWhCooling plant24 GWhUPS & losses6 GWhOffices & services3 GWh

The IT halls set a floor that never moves. Cooling adds the swing, and the swing sets the demand.

Fig 08-1 · Every half-hour of the yearGrid draw without storage · MW
00:0006:0012:0018:0024:00APRMAYJUNJULAUGSEPOCTNOVDECJANFEBMAR1913MW

Each column is a day from April 2026 to March 2027, each row a half-hour. There are no weekends and no shutdowns: the brighter afternoons are the cooling plant working through the Highveld summer, and the slow brightening across the year is new IT load as the halls fill.

01The brief

Cut the cost of the peak windows without touching the UPS, the tier design or a single customer rack.

02The constraint

Capital is approved on payback. Two spare panels on the 22 kV board, one per bus section, outside the secure perimeter.

03The risk

The recorded peak of 19 639 kVA sits within 2 % of the NMD, and the next hall would push the campus past it.

09 · The load

Flat by design,
swung by the weather.

The IT halls draw the same at 03:00 as at 18:00, so the peak windows carry a full share of the load. The cooling plant adds the swing on top, and it peaks in the summer afternoons.

Fig 09-1 · Average low-season weekdayMW
PEAKPEAK081624MW00:0006:0012:0018:0024:00
Fig 09-2 · The hottest weekday, 25 JanuaryPeak 18.7 MW
PEAKPEAK081624MW00:0006:0012:0018:0024:00
Fig 09-3 · What the peak periods cost, by monthR m active energy, without storage
0481216R mAprMayJunJulAugSepOctNovDecJanFebMar

June to August carry the winter peak price: 44 % of the year’s peak cost sits in those three months.

01The peaks cannot be moved

About 78 % of the peak-window load is customer IT. It cannot be shifted or switched off, only supplied differently.

02Winter costs 2.4 times more

The same kilowatt-hour costs R7.20 in a June peak and R2.99 in a November one, so the value is concentrated in three months.

03Summer sets the demand

Cooling averages 2.2 MW in winter and 3.0 MW the rest of the year. The year’s highest half-hour falls on a hot summer afternoon.

10 · The plant

Four blocks on
two spare bays.

Each 22 kV bus section takes two 2.5 MW / 5 MWh pairs. The plant sits upstream of every hall transformer and UPS, behind the Eskom meter, so the supply agreement and the critical path do not change.

Fig 10-1 · Single-line, as connectedSimplified
Eskom 22 kV · feeder AMegaflex Me02Npoint of supplyMETERincomerEskom 22 kV · feeder BMegaflex Me02Npoint of supplyMETERincomer22 kV BUS A22 kV BUS BHall 1tx + UPSHall 2tx + UPSMChillers A2 × 1.2 MWGSets A5 × 2 MWHall 3tx + UPSHall 4tx + UPSMChillers B2 × 1.2 MWGSets B5 × 2 MWNEW BAY ANEXUSN25002.5 MW · 22 kVAPEX A50005 MWh LFPNEXUSN25002.5 MW · 22 kVAPEX A50005 MWh LFPNEW BAY BNEXUSN25002.5 MW · 22 kVAPEX A50005 MWh LFPNEXUSN25002.5 MW · 22 kVAPEX A50005 MWh LFPSolaris™ EMSset-points down,telemetry up · BMS / SCADAMETER DATA → SOLARISSimplified single-line. Protection, earthing, auxiliary supplies and the LV side of each hall omitted.
Plant at a glancePer the range datasheets
Battery4 × APEX A5000, 20 MWh LFP
Usable18 MWh at 90 % depth of discharge
Conversion4 × NEXUS N2500, 48 × 215 kW
Power10 MW, 11 MVA maximum
ConnectionTwo 22 kV bays, one per bus
Round trip≥ 88 % AC–AC
ControlSolaris™ EMS, to the BMS by IEC 104
Footprint≈ 1 560 m² fenced yard
Fig 10-2 · The yardIndicative
EXISTING22 kV MV ROOMSTANDBY SETSBESS YARD · ≈ 46 × 34 mA5000 · 1N2500 · 1A5000 · 2N2500 · 2A5000 · 3N2500 · 3A5000 · 4N2500 · 422 kV CABLE TRENCH ≈ 90 mSERVICE ROADIndicative plan, not to scale. 3 m service clearance between rows.Footprint for the full plant ≈ 1 560 m², outside the secure data-hall perimeter.
Why four blocksFull year at FY2027/28 prices · indicative turnkey cost · NPV at 12 %
OptionRating22 kV baysCycles / yrGross savingPaybackNPV
2 × A50005 MW / 10 MWh1425R11.7 m2.8 yrsR73 m
4 × A5000 ◆10 MW / 20 MWh2365R21.9 m2.8 yrsR140 m
6 × A500015 MW / 30 MWh3286R25.9 m3.5 yrsR145 m

Two blocks pay back as fast but leave half of each peak on the bill and earn R10 m a year less. Six blocks cannot refill at midday without crossing the 17.4 MW ceiling, so they cycle less and need a third bay. Four blocks fill both bus sections and earn the most per rand. ◆ Selected.

11 · How it runs

Two cycles in winter,
one in the summer heat.

Solaris discharges through both peak windows and recharges at midday without crossing a 17.4 MW ceiling. In summer the chillers leave less room to recharge, so the plant cycles once and guards the ceiling.

Fig 11-1 · Wednesday 15 July 2026 · high seasonModelled · MW
PEAKPEAK081624MWCEILING 17.4 MWSOC100 %0 %+100−1000:0003:0006:0009:0012:0015:0018:0021:0024:00Load without batteryGrid draw with batteryDischargeChargeState of charge
Fig 11-2 · Wednesday 13 January 2027 · summer, low seasonModelled · MW
PEAKPEAK081624MWCEILING 17.4 MWSOC100 %0 %+100−1000:0003:0006:0009:0012:0015:0018:0021:0024:00Load without batteryGrid draw with batteryDischargeChargeState of charge

Cyan: energy the battery supplies, so the campus does not buy it. Grey: energy bought to recharge, at off-peak or standard prices and never above the ceiling. In January the midday recharge is small, and Solaris spends it holding the line. The lower strip is battery power (±10 MW) and the state of charge. At weekends the battery is held full as reserve.

365Equivalent full cycles a year
6.6GWhDelivered from the battery
1.9per dayWeekday cycles, winter
1.3per dayWeekday cycles, the rest of the year
12 · The bill

R21.9 m a year,
from four lines.

About 90 % of the saving is energy moved out of the peak. The lower notified demand adds the rest, or stays in hand as room for the next hall.

Fig 12-1 · Where the saving comes fromR m, FY2027/28
06.2512.518.7525R m19.7Peak energyshifted1.6Notifieddemand0.3Powerfactor0.2Networkdemand21.9Gross savingper year
Fig 12-2 · Monthly peak demandMVA, any hour
1415161718192021MVAAprMayJunJulAugSepOctNovDecJanFebMarBeforeAfterNMD beforeNMD after
Value streamHow it is earnedPer year
Peak energy shiftedPeak kWh bought at off-peak and standard prices, net of 12 % lossesR19.7 m
Notified demandNMD renewed at 18 000 kVA: generation, network and transmission capacityR1.6 m
Power factorPCS holds 0.99 at the board; the high-season reactive charge falls awayR0.3 m
Network demandMonthly peak in chargeable periods held under the ceilingR0.2 m
TotalR21.9 m
Fig 12-3 · Monthly bill, before and afterR m ex VAT, FY2026/27 rates
010203040R mAprMayJunJulAugSepOctNovDecJanFebMarWithout storageWith the plant

Bills are rebuilt line by line from the Megaflex schedule (500 V – 66 kV, zone 0): active energy by period and season, legacy, subsidy and ancillary charges, capacity charges on the notified demand, network demand on the monthly chargeable maximum, reactive energy in the high season and daily service charges. The notified-demand saving starts in year two. Keeping the 20 MVA instead leaves about 1.5 MW of new IT load inside it. A wheeled solar contract does not reach the evening peak, so this case holds with or without one. Diesel saved is not counted.

13 · Fifteen years

Less than four years
to pay back. Then it saves.

The operator buys the plant turnkey and we run it. The saving rises with the tariff; O&M and one augmentation block are the only costs after day one.

<4yrsSimple payback
39%Project IRR
140R mNPV at 12 %
8.4×The investment, returned
Fig 13-1 · Saving, running costs and cash returnedNominal R m · tariff +8.83 % in year one, then 7 % a year
020406080R m / yrY1Y2Y3Y4Y5Y6Y7Y8Y9Y10Y11Y12Y13Y14Y15Investment repaid8.4× the investment0×2×4×6×8×10×returnedSaving on the billO&M and augmentationCumulative cash returned, multiple of the investment
Fig 13-2 · What moves the NPVR m at 12 %
Peak / off-peak spread−15 %+15 %Discount rate14 %10 %Tariff escalation5 %9 %NMD reduction1 MVA3 MVAPlant availability95 %99 %BASE NPV R140 m

Even the worst single case leaves an NPV of R111 m.

Fig 13-3 · Usable energyMeasured curve · MWh
06121824MWh16.2 MWh design floor+1 A5000 in year 5Y1Y3Y5Y7Y9Y11Y13Y15Usable energy, fleetDesign floor

On the cell maker’s measured curve at 1.0 cycles a day. One more A5000 in year 5 keeps the fleet above 16.2 MWh for the term.

Indicative ownership termsFinal terms in the site proposal
StructureTurnkey supply, install and commissioning
OwnershipThe operator, from commissioning
O&M15-year service agreement, AMPROTEQ
Availability≥ 97 %, measured monthly
CapacityTested yearly; ≥ 16.2 MWh usable
AugmentationOne A5000 in year 5, in the plan
MonitoringSolaris, 24 / 7, to the BMS and NOC
AlternativeService agreement: fixed monthly fee
14 · Resilience & delivery

When the grid goes,
the sets do less.

The UPS and the sets keep their roles. On a published outage Solaris holds the charge, and once the sets have taken the 22 kV bus the battery carries part of the campus beside them.

Fig 14-1 · A scheduled outage, Tuesday 14 July: grid off from 18:00 to 20:00Modelled · MW
PEAKPEAK081624MWGRID OFFSETS 6.2 MWBATTERY 8.4 MW00:0003:0006:0009:0012:0015:0018:0021:0024:00GridBattery dischargeBattery chargeStandby setsCampus load

The battery carries 8.4 MW, 57 % of the campus, and the sets carry 6.2 MW. All ten sets stay on line, as the site’s rules require; each runs lighter. That saves about 4 100 litres of the 10 500 burned with the sets alone (generic set fuel curve). A two-hour curtailment of 3 MW needs no set at all.

Three layers, three jobs
LayerCarriesIn this plant
UPSThe IT load, from the first millisecondUnchanged
Standby setsThe whole campus, for as long as there is fuelStart on every outage, as now
APEX + NEXUSShares the campus load with the sets; carries curtailment aloneNew
Fig 14-2 · From load study to commercial operationIndicative, weeks
W0W4W8W12W16W20W24W28W32W36W40Load studyProposal and agreementGrid and protection studiesChange control and permitsSupply and delivery to siteCivils and cable trenchInstall, terminate, connectCommissioning and testsCommercial operationWeek 38AMPROTEQThe operator, with our supportGate
Risks we carry, and how
Grid-code or protection changeStudies before order; settings agreed with your engineer
Work near live hallsYard and cable outside the secure perimeter; change control
Cell ageingMeasured cell data; augmentation in the plan from day one

Illustrative case on a composite site; not a client project and not an offer. Modelled with Eskom’s Schedule of Standard Prices 2026/27 (Megaflex, 500 V – 66 kV, zone 0) and APEX A5000 / NEXUS N2500 ratings. Tariff escalation beyond 2027/28, the installed cost, the set fuel curve and all site data are assumptions.

15 · Questions

Asked by data-centre
buyers.

Does a battery replace our UPS?
No. The UPS protects the IT load over milliseconds to minutes and stays as it is. The battery plant works upstream at MV: on the bill every day, and beside the standby sets in an outage.
Where does it connect?
Usually on spare 22 kV bays, through NEXUS N2500 skids matched one-to-one to APEX A5000 blocks. Critical 400 V boards can add a PULSE transfer cabinet.
Is arbitrage worth it on a flat load?
Yes, because a flat load buys the full peak. In the modelled colocation campus, a 10 MW / 20 MWh plant takes a third of the peak energy off the bill and frees 2 MVA of notified demand.
The data-centre pack.

Two documents,
one decision.

The brief is the four-page case for storage beside the UPS. The case study runs the numbers on a modelled colocation campus, half-hour by half-hour, on the 2026/27 Megaflex tariff.

Cover of the AMPROTEQ data-centre sector brief, with the headline Battery storage for data centres
Sector briefAMP-SB-DC · Rev 1.1

Battery storage for data centres

4 pages · PDF · 1.7 MB

<4yrsSimple payback
34%Less energy bought in peak
2MVAOff the notified demand
Inside
  1. 01Where the money is
  2. 02The system: APEX A5000, NEXUS N2500, PULSE, Solaris
  3. 03Three layers of supply beside the UPS
  4. 04The return
Download the sector brief
Cover of the AMPROTEQ data-centre case study, with the headline Taking a colocation campus out of the peak
Case studyAMP-CS-DC · Rev 1.1

Taking a colocation campus out of the peak

8 pages · PDF · 2.0 MB

Illustrative case · composite site · not a client project

R20.2mOff the bill in year one
39%Project IRR over 15 years
10 MW/ 20 MWhOn two 22 kV bays
Inside
  1. 01The site
  2. 02The load
  3. 03The plant
  4. 04How it runs
  5. 05The bill
  6. 06Fifteen years
  7. 07Resilience & delivery
Download the case study

Figures in both documents are modelled on Eskom’s 2026/27 schedule and indicative costs. A site proposal replaces every one with numbers from your own data.

Next step

Start with your meter data.

Twelve months of interval data, your tariff schedule and your notified maximum demand are enough for a first sizing and an indicative capex, within five working days, at no cost.